| 1 | Click on a Task to view its details including guidance on how to complete the task within the system. |
| 2 |
Some tasks will have a specific action type associated with them, in which case you can click Do Now. The system will take you to the appropriate page to perform the necessary system steps. |
| 3 |
Other tasks will represent a key milestone. There are four in total:
|
| 4 | Some tasks require the user to be an approver on the procurement team to finalise the task or will be dependent on gateway approval being granted before they can be completed. |
The default tasks, timescales and assignments are set from the template, but users can add their own tasks or modify the due date field to reschedule the task, or change the assigned to field to re-assign to another User. Click Edit to edit these and other details.
Although optimised for eSourcing features, tasks in Atamis TM operate using the same activity management feature used elsewhere in Atamis 3.0 and will integrate with Outlook if required.
See the Activity Management section for more detail.
Action Types
Below is a list of available procurement tasks of type action type.
| Action Types | Notes |
| Approve Requirement Sections |
Completing this action type will approve the requirement sections set up on the project. Supplier cannot be invited or register interest until requirement sections are approved. |
| Issue an Amendment | If the users need to add or change any requirements during a Live Project, they can use this action type. |
| Publish Opportunity | Completing this action type will make the opportunity publicly available for suppliers to view and register their interest. |
| FTS/OJEU Notice | The user can draft a contract notice to submit to OJEU or the UK eNotification Service. |
| Contracts Finder Notice | The user can draft and publish a notice on Contracts Finder. |
| Suggest Suppliers |
The system will use the category associated with the project and suggest suppliers that match that category. Suppliers will not be invited or emailed at this stage. |
| Add Suppliers | This action type will allow the user to set up new suppliers with a portal account and add them to the project. |
| Invitation | The user can invite the suppliers to respond to the opportunity. |
| Use this task to send a message/email to all or selected bidders. | |
| New Procurement Stage | Used on multi-stage projects, this action type will move the project from one project stage to another. |
| Start Evaluation |
Upon closure of the Response Window, the user will be able to start the evaluation process and notify Evaluators using this action type. Evaluators must first be assigned records to evaluate before completing this action. |
| Create Contract Clause | |
| Generate Contract Document | |
| Award | The user can use this action type to award the contract to the successful bidder. |
| Custom | Action Type |
| Request Approval |
If the project contains tasks which require approval to proceed, the users can request approval to proceed by completing this task. This is connected to gateway approvals, and only needed if gateway approvals are set up on the project. |
| Evaluate Scores |
When all evaluators have completed scoring all responses, completing this action type will calculate the overall score totals. This action should be repeated to re-calculate totals whenever evaluator scores or override scores are entered. |
Updated