Atamis TM can be used to support the requirements of various specialist procurement procedures, some of which will be specific to the public sector.
Multi-Stage Procurements
Multi-stage procurement templates will have more than one response window open and close milestone. The Template will also have a Task type New Procurement Stage.
Click Do Now on this Task to move the stage on to the next value in this list:
- Pre-qualification
- Tender / RFx
- Tender / RFx - 2nd iteration
- Tender / RFx - 3rd iteration
- Tender / RFx - 4th iteration
Each Procurement Stage has its own separate requirement section(s). The new procurement stage task will mark any Requirement Sections associated with the completed Stage as archived.
It will then give you the opportunity to create a new requirement section covering requirements relating to the new stage.
Use the checkbox field Shortlisted? to keep track of suppliers to take forward to the next stage.
Projects with Lots
Assuming all lots are to be procured through the same process and with the same timescales, it is recommended to use a separate requirements section for each lot.
Alternatively, if each Lot is to be procured with different timescales, etc. each Lot should be set up as a separate Procurement Project. The Parent Contract field should then be used to link it to the master record.
It is possible to save this structure as a template. When you create a project from the template master record, the equivalent child (Lot) projects will be created for you and automatically linked to the master project record.
Frameworks and Call-Offs
If you have awarded a Framework to multiple suppliers you can set up a Call-off Template with the suppliers bidding already added.
When a user creates a project from the call-off template, approved suppliers will already be listed in the suppliers bidding section and the user can select which to invite to tender.
Please refer to Creating a Contract for further information
Dynamic Purchasing Systems
The process for calling off a DPS is as described in the frameworks and call-offs section above.
The master DPS project itself need to:
- use a procedure with the property DPS = TRUE
- have a response window closes date set to a future date that reflects the last opportunity that a supplier can register for the DPS
- the project must not have multiple stages
- have a requirement section containing the pre-qualification criteria if required
- be published to the tender opportunities site
Use picklist requirements of type Pass/Fail and set up requirements options with Pass/Fail criteria.
This will speed up the decision process.
With the above settings, suppliers can register their interest and complete the qualification criteria and submit their response at any time.
Internal users are notified when a new supplier submits their responses to the DPS criteria.
If Pass/Fail auto-scoring has been set up, Start Evaluation Task can be used and the Evaluate Scores button to evaluate whether the supplier qualifies for the DPS.
If they do, add them as a Supplier Bidding on the DPS Call-Off Template.
Updated